Rehabilitation of Pumping Station PS3

ClientState Company for Oil Projects
SupplierPetrofac Mechanical Services
LocationNajaf - Iraq
SkillsElectrical / Mechanical / Installation

Rehabilitation of Pumping Station PS3 - Two Turbopumps GE Frame 3 Units

The Project was including rehabilitation of two turbo pumps based on Frame 3 GE gas Turbine and Nuova Penguin Centrifugal pumps in PS3 Pumping station in Najaf- Iraq along the strategic pipeline, the work included the Mechanical, Electrical, Control & Instrumentation work activities, the Project activities was:

  • Overhauling the GE Fram3 Turbines and Pumps.
  • Supply and installation of new two intake filters.
  • Supply and installation of Air compression package.
  • Upgrading, installation and calibration of field instrument, and loop testing.
  • Valve’s actuators sizing and replacement.
  • maintenance of the auxiliary systems.
  • Cable laying and signaling.
  • Electrical & Control Panels installation.
  • Commissioning and Start-up of the whole pump station.